Creating a Project Schedule Project Management Help

In Its simplest, form, a project schedule is a list of tasks with their respective due dates. In its most developed form, a project schedule is a dynamic tool that defines not only what needs to be completed and when, but also how the project tasks impact upon one another. For a project to be successful, it generally must be completed as defined, within the estimated time, and within budget. So what happens when one task cannot be completed on schedule?

What impact does that have on the completion of subsequent tasks? How does that affect the costs related to the project? Will the resources assigned to the project be sitting around with nothing to do while they wait for a task to be completed?

What happens if a task is completed early? Can the next task begin or must it wait until a prescribed date or time? Unless you, as project manager, can answer these questions, the success of the project is at risk. Microsoft Project can help you answer these questions long before something outside of your control impacts the project plan, and can prepare you for any possible contingency.

Identifying Predecessor and Successor Tasks

Linking tasks is Project’s way of showing you how tasks are related to each other, By Hnking tasks, Project can make the necessary adjustments to the schedule whenever there are changes that affect the start or completion of other tasks.

No matter how invested you are in a schedule, you can’t move an offtceIf the moving van doesn’t arrive; you can’t train new staff if they haven’t been hired yet. By linking tasks, you create a project schedule that is realistic and logical, updates automatically when tasks are delayed or completed ahead of schedule, and provides you with a clear plan of the resource/needs at various points throughout the project.

When tasks are linked, the task that must be started or completed first is canned the predecessor and the task that depends on the predecessor is called the successor.

In Figure 8.1, it’s clear that before the architectural drawings can be completed, suitable  office space must be found. Before offices can be assigned, the drawings must be completed, and before furniture can be order the offices must be assigned.

If all these tasks are completed at the same time or in a different order, the drawings won’t fit the space, too much furniture might be ordered, and people might be assigned to offices that didn’t even exist. The sequencing of the tasks is essential to each task’s successful outcome and one task is dearly dependent on the other. The arrow between tasks shown in Figure 8.1 plainly shows the dependency relationship. The arrow points to the dependent, or successor, task. In this example, Task 3 is a successor of 2, Task 4 is a successor of 3, and Task 5 is a successor of 4.

When these tasks are actually underway, the relationships might not be as clear. Figure 8.2 shows the comparison of actual Start and Finish Dates with the Baseline, or planned Start and Finish. In Figure 8.2, you can see that Task 2, Find suitable office space, took a day longer than planned~to complete. As a result, Task 3, Create space drawings, which is dependent on Task 2, could not start on schedule. Task 3’s start  was delayed by several days. Because the task started behind schedule, it was decided that as soon as a general sketch of the office was laid out, offices could be assigned (Task 4), and furniture could be ordered (Task 5). This decision actually benefited by the project by putting it about four days ahead of schedule.

Although not every task in a project may have a predecessor or successor, defining those that do can help develop a realistic schedule and keep the project on track ..

Using Different Types of Relationships

Defining task relationships is not always as straightforward as the terms predecessor and successor suggest. The most common type of relationship, referred to. a finish-to-start relationship, is a relationship in which one task, the successor, can’t start until the predecessor is completed. However, not all relationships fit this pattern. With Microsoft Project, you can define four different types of relationships between tasks.

Finish-ta-Start (FS) A finish-ta-start relationship is the default relationship in Project, and it is the most com- . mon type of dependency. In a finish-to-start dependency, one task cannot start until another task finishes. For example, you cannot distribute new office furniture until the furniture arrives from the vendor. Figure 8.3 shows a typical finish-to-start dependency.

Start-ta-Start (55)

Astart-to-start dependency is a dependency in which one task cannot start until another task starts. In this type of dependency, the successor task may be able to start immediately or soon after the predecessor starts, rather than waiting until the predecessor task finishes. To use an everyday example of a start-to-start relationship, baking holiday cookies is an obvious predecessor to decorating the cookies. However, you don’t need to wait until all of the cookies are baked to begin decorating. By adding lead time to the decorating task, you can start the decorating as soon as the first batch comes out of the oven and cools a bit. Figure 8.4 demonstrates a start-to-start relationship in the Office Decentralization project.

One of the groups of tasks in this project is related to hiring staff for the new office. In this example, as soon as the people responsible for hiring begin reviewing resumes, they can schedule interviews with likely candidates. A day of lead time allows the interview team to contact the candidates and set up the interviews .

Finish-to-FinisH {FF}

When a finish-to-finish dependency is established, one task cannot finish until another task finishes. In this type of dependency, start dates are irrelevant to the relationship. What matters is that the predecessor finishes before or at the same time as the successor. Let’s say, for example, that two interview teams are responsible for interviewing and coming up with a list of hiring recommendations. The team that hires sales staff must finish before the office hiring team finishes to make sure that appropriate office staff is hired to meet the needs of the sales managers.

In Figure 8.5, the task of interviewing was divided into two separate tasks: interviewing sales staff and interviewing office staff. Each task has a start-to-start relationship with reviewing resumes. In addition, the two interviewing tasks have a finish-to-finish relationship with each other. Interviewing the sales staff must be completed first, so it is the predecessor task. Interviewing the office staff cannot be completed until the sales staff interviews are complete, so interviewing the office staff is the successor task.

Start-to-Finish (SF)

The last type of dependency is a start-to-finish dependency. In this type of relationship, the finish date of one task is dependent on the start date of the other task.

For example, if painting the new office space is scheduled to start in the afternoon of March 26, the paint should be delivered freshly mixed in the morning of March 26. If the mixing is completed too soon before the painting begins, it may have to be remixed on-site. If the painting is delayed because the painters are held up on another job, the paint should not be delivered. Figure 8.6 shows the start-to-finish relationship between these two tasks .Although the mixing of the paint occurs first chronologically, the process of mixing and delivering the paint is dependent on the start date of the painting. So, in this instance, painting is viewed as the predecessor and mixing is the successor.

Posted on November 26, 2015 in Scheduling And Linking Project Tasks

Share the Story

Back to Top